| Testing and Commissioning (IM5)
Hazards | Risk Rating | | Electrical shocks to site staff | High | | Damage to equipment | Medium | | | | | | | | | |
Planned Methods To Reduce Risks
If necessary, a permit to work system will be operated.
Only competent persons with suitable test equipment shall carry out the testing and commissioning.
Planning will include liaison with other contractors and those in control of the premises to ensure that all are aware of the work to be carried out.
The electrical contractor shall carry out all testing and commissioning strictly in accordance with the current legislation.
|